Summary:
The following sealed bids were received in response to the subject solicitation:
Supplier
|
Bid Amount
|
DB Civil Construction, LLC, Ormond Beach, FL
|
$820,425.00
|
Cobb Site Development, Inc., Wauchula, FL
|
$845,430.04
|
Prime Construction Group, Inc., Orlando FL
|
$908,025.00
|
Cathcart Construction Company-Florida, LLC, Oviedo, FL
|
$1,113,075.00
|
Valencia Construction Group, Inc., Winter Garden, FL
|
$1,206,960.00
|
This Contract is for the installation of 10-inch force main and related appurtenances along South Osceola Ave. from E. Jersey Street to E. Kaley Street.
The Procurement and Contracts Division and Public Works Department have evaluated these bids and recommend award to the lowest, responsive and responsible bidder, DB Civil Construction, LLC., of Ormond Beach, FL for the South Osceola Avenue Sewer Improvements project, in the amount of $820,425.00.
DB Civil Construction, LLC., M/WBE Participation Plan for this contract totals 6.9% and is as follows:
Central Florida Construction Walls, Inc. |
MBE |
$17,480.00 |
2.10% |
EM Paving |
MBE |
$14,750.00 |
1.80% |
Superior Concrete, LLC |
MBE |
$24,705.00 |
3.00% |
Total MBE Participation |
|
$56,935.00 |
6.90% |
|
Recommended Action:
Approval of award to DB Civil Construction, LLC., and authorize the Chief Procurement Officer to enter into an agreement with DB Civil Construction, LLC., from Ormond Beach, FL as indicated above in the amount of $820,425.00, subject to review and approval by the City Attorney’s Office. |