Summary:
On January 11, 2016, City Council approved an Agreement with Garney Companies, Inc., in the amount of $4,152,382.82, and authorized the Chief Procurement Officer (CPO) to execute said Agreement. These improvements for the West Central Blvd. Gravity Sewer, Roadway, Utility, and Streetscape Project were designed to provide the required sanitary sewer capacity for the proposed MLS Stadium located at W. Central Blvd. and Parramore Avenue.
Approval is now requested for the Phase 2 OUC Duct Bank Addendum in the Guaranteed Maximum Price (GMP) of $2,732,865.26. These improvements will allow for the removal of the overhead OUC power lines and poles by installing an underground duct bank with feeds to adjacent properties and street lighting. The limits of the project are along W. Central Blvd. from Glenn Lane to Hughey Avenue.
Garney Companies, Inc. has committed to 6.94% M/WBE participation for this phase. Given that the scope of work is specialized and has limited opportunities for subcontracting, it has been determined that the M/WBE good faith requirements have been met. |
Recommended Action:
Approve the Phase 2 Addendum with Garney Companies, Inc., in an amount not to exceed $2,732,865.26, and authorize execution of Addendum by the CPO, subject to review and approval by the City Attorney’s Office. |