CITY OF ORLANDO
COUNCIL AGENDA ITEM


Items Types:
Business and Financial Services
For Meeting of:
July 13, 2015
District: ALL From:
Contract ID: Document Number:
Exhibits: Yes On File (City Clerk) : Yes Draft Only: No
Grant Received by City?: No

Subject:
Award to Altair Environmental Group, LLC, for Concrete Sidewalk Repairs and Construction, IFB15-0290

Summary:

The following sealed bids were received in response to the subject solicitation:

Supplier Bid Amount
Altair Environmental Group, LLC, Longwood, FL $ 769,350.00
RMS Construction Group, Orlando, FL $ 780,050.00
Johnson-Laux Construction LLC, Orlando, FL $ 823,620.00
JPR Universal Contractors, LLC, Clearwater, FL $ 824,890.00
Schuller Contractors Incorporated, Orlando, FL $ 899,150.00
Tagarelli Construction, Inc., Tarpon Springs, FL $ 999,400.00
Design Build Engineers & Contractors, Orlando, FL $ 1,139,800.00
Evans Contracting Services, Inc., Middleburg, FL $ 1,415,750.00

A bid was also received from Parthenon Construction, however it was determined to be non-responsive.

The Procurement and Contracts Division and the Streets and Stormwater Division have evaluated these bids and recommend award to the lowest, responsive and responsible bidder, Altair Environmental Group, LLC, for concrete sidewalk repairs and construction.

The initial contract term is one (1) year with an option to renew for four (4) additional one (1) year terms.  This is an indefinite quantity contract.  Actual expenditures will vary as usage will be on an as-needed basis at the established unit prices and available funding.  Based on prior usage reports and information provided by the primary user, the estimated annual expenditure is $800,000.00.

The Altair Environmental Group, LLC M/WBE Participation Plan for this contract is as follows: 

Nicole Transport & Excavating, Inc. MBE $ 138,483.00 18.00% Trucking, Site Work, Demolition and Excavating
Flash Rite, Inc. WBE $ 46,161.00 6.00% Trucking/Hauling
Total M/WBE $ 184,644.00 24.00%

Fiscal & Efficiency Data:

Recommended Action:

Approval of award to Altair Environmental Group, LLC and authorize the Chief Procurement Officer to enter into an agreement and subsequent renewals with Altair Environmental Group, LLC as indicated above in the estimated annual amount of $769,350.00, subject to review and approval by the City Attorney’s Office.



Agenda Item attachment(s) on file in the City Clerks Office.

Note: All agenda items must be in the City Clerk's office by Noon Friday, six(6) business days prior to the regular Monday City Council meeting.

Contact: David Billingsley
Approved By:

Department Date and Time
Budget Outside Routing Approval 7/2/2015 8:28 AM
City Clerk 7/2/2015 8:33 AM

ATTACHMENTS:
Name: Description: Type:
Fiscal_Impact_Statement_Form_IFB15-0290.docx FIS IFB15-0290 Fiscal Impact Statement
Bid_Tab__IFB15-0290_.pdf Bid Tab IFB15-0290 Backup Material
2015.concrete.sidewalk.repair.and.construction.ifb15-0290.revised_(1).pdf MWBE Award Recomendation Backup Material
Award_Recomendation.pdf Bid Evaluation - IFB15-0290 Backup Material

"Enhance the quality of life in the City by delivering public services in a knowledgeable, responsive and financially responsible manner."