CITY OF ORLANDO
COUNCIL AGENDA ITEM


Items Types:
Business and Financial Services
For Meeting of:
May 18, 2015
District: 5 From:
Contract ID: Document Number:
Exhibits: Yes On File (City Clerk) : Yes Draft Only: No
Grant Received by City?: No

Subject:
Contract with McCree General Contractors, Inc. for Design Build services for the Permanent Fire Station No. 2 project

Summary:

Based upon a prior Council approval to use McCree for design build services for a total of three stations, on October 20, 2014 City Council approved a Guaranteed Maximum Price (GMP) contract ($140,450) with McCree for site construction services for the Temporary Fire Station No.2 and planning and preliminary design services for the future permanent Fire Station No. 2. The Temporary station was completed in December 2014 on the east side of the parcel located at the NE corner of Robinson Street and Hames Avenue. The Temporary Station became fully operational in early January 2015. Under another contract, the station housing (modular structure) is provided to OFD by a private company via an 18 month lease.

With the modular lease set to expire in mid 2016, it is important to progress towards the permanent station. A portion of the funding approved by Council on October 20, 2014 was used to facilitate preliminary planning and 30% design plans, which were recently completed. McCree used these plans to prepare a GMP for the Permanent Station (four bays). GMP negotiations were completed with McCree in early May of this year. The GMP is $4.6M. Savings to the City were gleaned as a result of using the pro-typical station design which was previously designed and implemented by McCree for Fire Station No. 7. The Permanent Station will be constructed on the west side of the parcel at the NE corner of Robinson Street and Hames Avenue (right beside the temporary station). The permanent station is scheduled for completion and full operation prior to the expiration of the temporary station modular lease.

McCree has worked closely with the City’s MBE/WBE department throughout the delivery of the Temporary Station and during the initial phases of the Permanent Station. They will continue to do so. McCree exceeded the City’s goals on the Temporary Station and has committed /pledged to meet and/or exceed the City’s required goals pertaining to the Permanent Fire Station No.2 GMP.


Fiscal & Efficiency Data: Sufficient funding will be available in the City of Orlando Project No. OFR0006P & CIP0164P

Recommended Action:

Approve the GMP Proposal with McCree General Contractors, Inc. and authorize the Chief Procurement Officer to enter into an agreement with McCree General Contractors, Inc. as indicated above in the amount not to exceed $4,600,000.00, subject to review and approval by the City Attorney's Office.



Agenda Item attachment(s) on file in the City Clerks Office.

Note: All agenda items must be in the City Clerk's office by Noon Friday, six(6) business days prior to the regular Monday City Council meeting.

Contact: David Billingsley
Approved By:

Department Date and Time
Budget Outside Routing Approval 5/8/2015 3:29 PM
City Clerk 5/8/2015 3:32 PM

ATTACHMENTS:
Name: Description: Type:
FIS_Permanent_Fire_Station_2_McCree.doc FIS Fire Station #2 GMP Backup Material
FIRE_STATION_2_McCree_GMP_for_Contract_May_7_2015.pdf GMP - Fire Station #2 Backup Material
Fire_Station_2_Design_Build_Agreement_2015.pdf Agreement - Fire Station #2 Backup Material

"Enhance the quality of life in the City by delivering public services in a knowledgeable, responsive and financially responsible manner."