| | | | | | | |  | CITY OF ORLANDO AGENDA ITEM
|
|
| | | | | | | |
Items Types: Business and Financial Services
| For Meeting of: 1/12/2015
| District:6 | On file (City Clerk):Yes |
|
| | | | | | | | Subject: | Award contract to Prime Construction Group, Inc. for Lake Angel Expansion Project No. CIP009_G, IFB15-0026 | Summary: | The following sealed bid was received in response to the subject solicitation:
VENDOR
|
BID AMOUNT
|
Prime Construction Group, Inc., Orlando, Florida
|
$ 1,899.900.00
|
This contract will consist of expansion to an existing retention pond which was created during the original construction of I-4. Expansion is being done to accommodate future I-4 expansion and to reduce flooding potential in the stormwater basin area of the pond.
The Procurement and Contracts Division and the Public Works Department have evaluated the submittal and recommend awarding the contract to Prime Construction Group, Inc. the lowest responsive and responsible bidder.
Since this project is part of the EPA program, the MBE office is not providing a MWBE memo. However, it is noted that good faith efforts are substantiated. Prime Construction Group, Inc. has proposed to utilize the following MBE & WBE percentages.
MBE 9.39 %
WBE 5.32%
| Fiscal and Efficiency Data: | See attached. | Recommended Action: | Authorize the Chief Procurement Officer to execute a contract with Prime Construction Group, Inc., in the amount of $1,899,900.00, as indicated above, subject to review and approval by the City Attorney's Office. | Contact: | David Billingley |
|
ATTACHMENTS: | File Name | Description | Type | Fiscal_Impact_Statement_IFB15-0026.doc | FIS IFB15-0026 | Backup Material | Bid_Tabulation_12-12-14.pdf | Bid Tab IFB15-0026 | Backup Material | Dept_approval_memo.pdf | Department Award Memo IFB15-0026 | Backup Material |
|
| | | | | | | |
 "Enhance the quality of life in the City by delivering public services in a knowledgeable, responsive and financially responsible manner." |
|
|