Summary:
On August 5, 2013, City Council authorized the Chief Procurement Officer to execute the subject contract in the not-to-exceed amount of $552,351.76, subject to the review and approval of the City Attorney's Office.
This amendment includes additional work involving drainage improvements, sanitary sewer upgrades, and construction complexities that exceeded the original scope by an amount of $147,733.57, plus $49,500 to design OUC water distribution facilities, for a total change of $197,233.57.
|
Recommended Action:
Authorize
the Chief Procurement Officer to execute an amendment to the subject contract
with Wantman Group, Inc., in the amount
of $197,233.57, subject to review and approval by the City Attorney's Office.
|