The exact value of some items included in the MOU are still being determined and funding will be identified in future budget amendments or through the annual Capital Improvement Plan development and approvals. An estimated value of items included in the MOU are below:
Value of land transferred to UCF - $20 million
Value of the existing Center for Emerging Media (former Expo Center) building - $22.5 million
Realignment of Livingston and BRT project (partially funded by TIGER II) - $16.5 million
Stormwater Improvements - $4 million
Construction of Livingston Street from Terry Avenue to Parramore Avenue - $2.5 million
CentroPlex Garage Lease - $2,017,690 in in-kind parking from the City over five years
· The City will receive income from UCF in the amount of $250,890 for the rental of the CentroPlex 1 Garage. The City will save an average of $175,000 per year in operations and maintenance costs for the garage.
· If all 603 spaces in the CentroPlex garage and the retail spaces were leased at current market rates, the maximum revenue the City would receive on the garage is $654,428 per year (after operations and maintenance costs).
· As such, the City is providing UCF with $403,538 in in-kind parking costs based on current market rates. This is $2,017,690 over five years.
CSX Rail Spur Acquisition - $142,500
Total City Commitment – Nearly $68 million
In addition, Creative Village Development LLC has committed $7.7 million toward the project for a total commitment from the City and its development partner to exceed $75 million.