CITY OF ORLANDO
COUNCIL AGENDA ITEM


Items Types:
Business and Financial Services
For Meeting of:
April 14, 2014
District: ALL From:
Contract ID: Document Number:
Exhibits: Yes On File (City Clerk) : Yes Draft Only: No
Grant Received by City?: No

Subject:
Advisory Committee Ranking for Design Build Services of Orlando Police Headquarters, RFP14-0133

Summary:

A Request for Proposal (RFP) was issued on January 6, 2014, to select a qualified firm to provide Design Build Services for the Orlando Police Department Headquarters. Seven (7) proposals were received and reviewed by an Advisory Committee (Committee) comprised of the following individuals:

Thomas Connery, Division Manager, CIP Public Works

Nathaniel Boyd, Energy Project Manager, Facility Management Division

Eric Clapsaddle, Police Officer

Susan Manney, Police Captain, Police Department Administration

Byron Raysor, Minority and Women Owned Business Enterprise Office

Based on the information presented in the Proposals and the evaluation criteria set forth in the RFP, the firms were ranked by the Committee in the following order for short-listing:

Ranking Firm Location
1 H.J. High Construction Orlando, FL
2 Moss & Associates, LLC Orlando, FL
3 Gilbane Building Company Orlando, FL
4 McCree Design Builders, Inc. Orlando, FL
5* James A. Cummings, Inc. Orlando, FL
5* PCL Construction Orlando, FL
7 Skanska USA Building, Inc. Orlando, FL
*Tie Ranking  
 

The three (3) top ranked firms conducted presentations to the Committee and based on the evaluation criteria set forth in the RFP, the shortlisted firms were ranked in the following final order:

Ranking Firm Location
1 H.J. High Construction Orlando, FL
2 Moss & Associates, LLC Orlando, FL
3 Gilbane Building Company Orlando, FL
 
 
H.J. High Construction's M/WBE Participation Plan for this contract is as follows:
 
Rhodes+Brito Architects MBE 21.6% Design
Milan Engineering MBE 18.0% Design
WBQ Design & Engineering MBE 3.5% Design
JCB Construction, Inc. MBE 10.3% Construction
OLP Construction, Inc. MBE 7.4% Construction
ACE Rebar and Construction MBE 0.7% Construction
     
       
BASE Consultants WBE 9.0% Design
Mims Construction Services WBE 4.1% Construction
H.I.S. Painting, Inc. WBE 1.8% Construction
Southeastern Surfaces & Equipment WBE 1.2% Construction
Window Interiors WBE 0.3% Construction
     
 

Fiscal & Efficiency Data:

Recommended Action:

Approval of the ranking established by the Advisory Committee and approval and authorization for the Chief Procurement Officer to negotiate and execute a contract with the top ranked firm, H.J. High Construction, as indicated above. If negotiations are not successful with the top ranked firm, approval and authorization for the Chief Procurement Officer to negotiate with the remaining firms in ranked order and execute a contract as indicated above, with the highest ranked firm with whom agreement is reached. The final negotiated agreement will be subject to review and approval by the City Attorney’s Office.



Agenda Item attachment(s) on file in the City Clerks Office.

Note: All agenda items must be in the City Clerk's office by Noon Friday, six(6) business days prior to the regular Monday City Council meeting.

Contact: David Billingsley
Approved By:

Department Date and Time
Budget Outside Routing Approval 4/2/2014 1:46 PM
City Clerk 4/2/2014 2:15 PM

ATTACHMENTS:
Name: Description: Type:
1st_Committee_Meeting_Minutes.pdf 1st Committee Meeting Minutes Backup Material
2nd_Committee_Meeting_Minutes.pdf 2nd Committee Meeting Minutes Backup Material