Summary:
A Request for Proposal (RFP) was issued on January 6, 2014, to select a qualified firm to provide Design Build Services for the Orlando Police Department Headquarters. Seven (7) proposals were received and reviewed by an Advisory Committee (Committee) comprised of the following individuals:
Thomas Connery, Division Manager, CIP Public Works
|
Nathaniel Boyd, Energy Project Manager, Facility Management Division
|
Eric Clapsaddle, Police Officer
|
Susan Manney, Police Captain, Police Department Administration
|
Byron Raysor, Minority and Women Owned Business Enterprise Office
|
Based on the information presented in the Proposals and the evaluation criteria set forth in the RFP, the firms were ranked by the Committee in the following order for short-listing:
Ranking
|
Firm
|
Location
|
1 |
H.J. High Construction |
Orlando, FL |
2 |
Moss & Associates, LLC |
Orlando, FL |
3 |
Gilbane Building Company |
Orlando, FL |
4 |
McCree Design Builders, Inc. |
Orlando, FL |
5* |
James A. Cummings, Inc. |
Orlando, FL |
5* |
PCL Construction |
Orlando, FL |
7 |
Skanska USA Building, Inc. |
Orlando, FL |
*Tie Ranking |
|
The three (3) top ranked firms conducted presentations to the Committee and based on the evaluation criteria set forth in the RFP, the shortlisted firms were ranked in the following final order:
Ranking
|
Firm
|
Location
|
1 |
H.J. High Construction |
Orlando, FL |
2 |
Moss & Associates, LLC |
Orlando, FL |
3 |
Gilbane Building Company |
Orlando, FL |
H.J. High Construction's M/WBE Participation Plan for this contract is as follows:
Rhodes+Brito Architects |
MBE |
21.6% |
Design |
Milan Engineering |
MBE |
18.0% |
Design |
WBQ Design & Engineering |
MBE |
3.5% |
Design |
JCB Construction, Inc. |
MBE |
10.3% |
Construction |
OLP Construction, Inc. |
MBE |
7.4% |
Construction |
ACE Rebar and Construction |
MBE |
0.7% |
Construction |
|
|
|
|
|
|
|
|
BASE Consultants |
WBE |
9.0% |
Design |
Mims Construction Services |
WBE |
4.1% |
Construction |
H.I.S. Painting, Inc. |
WBE |
1.8% |
Construction |
Southeastern Surfaces & Equipment |
WBE |
1.2% |
Construction |
Window Interiors |
WBE |
0.3% |
Construction |
|
|
|
|
|
Recommended Action:
Approval of the ranking established by the Advisory Committee and approval and authorization for the Chief Procurement Officer to negotiate and execute a contract with the top ranked firm, H.J. High Construction, as indicated above. If negotiations are not successful with the top ranked firm, approval and authorization for the Chief Procurement Officer to negotiate with the remaining firms in ranked order and execute a contract as indicated above, with the highest ranked firm with whom agreement is reached. The final negotiated agreement will be subject to review and approval by the City Attorney’s Office.
|