CITY OF ORLANDO
COUNCIL AGENDA ITEM


Items Types:
Community Redevelopment Agency (CRA)
For Meeting of:
February 24, 2014
District: 5 From:
Contract ID: Document Number:
Exhibits: Yes On File (City Clerk) : Yes Draft Only: No
Grant Received by City?: No

Subject:
Downtown Facade and Building Stabilization Program Funding Agreement between the Community Redevelopment Agency and Real Thread Inc. for 400B Pittman Street

Summary:

The Downtown Façade and Building Stabilization Program offers a three-year, interest-free deferred loan for façade and/or building stabilization improvements to existing properties within the Downtown Community Redevelopment Area ("Downtown CRA"). The Program, which was approved by the CRA on July 30, 2012, provides assistance with costs related to exterior physical improvements throughout the entire Downtown CRA, as well as building stabilization improvements within the Parramore Heritage Area of the Downtown CRA. The Program offers matching funds to off-set the costs of eligible improvements.

Real Thread, Inc. leases a property located at 400B Pittman Street and has applied for assistance under the Program for both façade and building stabilization improvements, including parking area improvements, installation of a new wood entry deck, reworking of existing canopies, installation of new HVAC units, exterior cleaning and painting, and installation of entryway glass and doors.

The Program provides an opportunity for the CRA to reimburse up to 50 percent of the project cost, based upon the lowest estimate, but not to exceed $40,000, for eligible properties making both façade and building stabilization improvements to commercial buildings within the Parramore Heritage Area of the Downtown Orlando CRA. The owner's capital investment for all building improvements is estimated at over $350,000.00. After obtaining three quotes for eligible improvements based on current Program guidelines, the lowest bid came in at $105,968, thus they are eligible for funding assistance up to $40,000.

The Downtown Façade Grant Review Committee convened on February 3, 2014 and made a recommendation of approval for funding assistance of up to $40,000 toward the proposed improvements at 400B Pittman Street.


Fiscal & Efficiency Data:

Recommended Action:

Approval of the Downtown Façade and Building Stabilization Program Funding Agreement between the Community Redevelopment Agency and  Real Thread Inc.  for 400B Pittman Street, subject to review and approval of the City Attorney's Offfice, and authorizing the Chair of the CRA and Executive Director to execute such Funding Agreement.

 


Agenda Item attachment(s) on file in the City Clerks Office.

Note: All agenda items must be in the City Clerk's office by Noon Friday, six(6) business days prior to the regular Monday City Council meeting.

Contact:
Approved By:

Department Date and Time
Budget Outside Routing Approval 2/14/2014 8:18 AM
Real Estate and Finance Attorney 2/14/2014 9:07 AM
City Clerk 2/14/2014 10:17 AM

ATTACHMENTS:
Name: Description: Type:
FIS_RealThreadInc.doc FIS RealThread Backup Material
RealThreadFundingAgreement.pdf Real Thread Inc Funding Agreement Backup Material
RealThreadApplicationPackage1.pdf Real Thread Inc Application Package (1 of 2) Backup Material
RealThreadApplicationPackage2.pdf Real Thread Inc Application Package (2 of 2) Backup Material
400BPittmanPlans1.pdf Real Thread Inc Complete Plans (1 of 2) Backup Material
400BPittmanPlans2.pdf Real Thread Inc Complete Plans (2 of 2) Backup Material

"Enhance the quality of life in the City by delivering public services in a knowledgeable, responsive and financially responsible manner."